Springfield City Schools

Kapp Construction was the Construction Manager partner selected to supervise the construction of 16 schools with a schedule that spanned 7 years. With a supervisor on site full time, Kapp managed all of the trades and subcontractors as well as the construction schedule. Using Prolog Construction Management Software, Kapp effectively and efficiently managed the day-to-day tasks at as many as 6 schools under construction at any one time.

Each facility included state-of-the-art technology and teaching tools in the learning areas, and security measures inside and out of the facilities were critical. The schools used automatic locking devices on doors, security cameras and motion sensors throughout, and occupancy sensors and timers on lighting.
 
 
Project Size: 
$175,727,000
 
Type Of Construction:
Construction Manager
 
Completed In:
2008

Owner's Representative:
Scott Spears, (937) 435-0736